Lots of action on the site this week. The crusher is still crushing material to create new clean fill, front end loaders are moving the fill into place, cement trucks are pouring more foundations and, in the background, work is progressing on placement of drain lines.
The yellow tape marks the water table soil test pits which will be refilled as soon as the all-clear comes back from DEM.